Academy and Woodmen Interchange Update: construction schedule through 10/24

Published October 20, 2009 by Carrie

Academy and Woodmen intersection - looking northwest from the east side of the intersection
The Academy and Woodmen interchange construction project continues. Here’s the major points of the 7-day outlook for this week (through October 24th):

  • Removal of Einstein Bagels and Albertacos Building
  • Removal of medians along Academy
  • Alignment changes:
    • Continued temporary alignment changes for east bound and westbound Woodmen between Academy and the eastern Sam’s Club entrance.  Entrances to Woodmen Commons Shopping Center remain open and there will continue to be two lanes on both eastbound and westbound Woodmen Road.
    • Temporary alignment change from Shrider Road to Woodmen on Academy Blvd.  Three travel lanes on Northbound and Southbound Academy will be maintained
    • Temporary alignment change from Woodmen Road to York Road on Academy Blvd.  Three travel lanes on Northbound and Southbound Academy will be maintained.

You can view the complete schedule at WoodmenRoad.com.

Contact Us

(719) 231-9043

jeremy@circagroup.com

11508 Shaugnessy Rd.
Colorado Springs, CO 80908

Office open by appointment only

Copyright 2008 - 2022
Circa Group, LLC

Equal Housing Opportunity

Privacy Policy